Oytal Small Hydropower Plant

Construction of the Oytal Small Hydropower Plant on the Tar River with three hydro units and phased commissioning of capacity.

Project description

Construction of the Oytal Small Hydropower Plant on the Tar River with three hydro units and phased commissioning of capacity.

Financial indicators

Funding required
8,200,000 USD

Key parameters

Design capacity
7.2 MW: three units of 2.4 MW each
Estimated output
54 mln kWh per year
Design head
80 m; flow rate 9 m³/s
Stages
First stage — 2.4 MW, subsequent — 4.8 MW

Project location

Tar River, approximately 5–7 km upstream from Oytal village, Kara-Kulja district, Osh region.

Approximate location. Exact site and participation conditions — upon request to the National Investment Agency.

Funding required
8,200,000 USD
RegionOsh region

Participation in the project

National Investment Agency

Contact the agency to receive a presentation, discuss participation terms, and next steps. The selected project will be automatically indicated in your inquiry.