Electrification of the Lugovaya — Balykchy railway
Electrification of the Lugovaya — Balykchy railway section with transition to electric traction.

Open for investment
1 / 1
Illustration from the passport
Project description
Electrification of the Lugovaya — Balykchy railway section with transition to electric traction. The project provides for power supply to the line and works on maintenance depots in Bishkek and Balykchy.
Financial indicators
- Total cost
- 297,670,000 USD
- Funding required
- 297,670,000 USD
Key parameters
- Section length
- 321.5 km; of which 261.2 km in Kyrgyzstan and 60.3 km in Kazakhstan
- Track
- Single track, gauge width 1 520 mm
- Stations and passing loops
- 18 stations and 3 passing loops
- Electrification
- 274.52 million USD
- Power transmission lines
- 15.7 million USD
- Maintenance depots
- 5.15 million USD
- Other expenses
- 2.3 million USD
Project location
Lugovaya — Bishkek — Tokmok — Balykchy railway corridor; Chuy and Issyk-Kul regions, section in Kazakhstan.
Approximate location. Exact site and participation conditions — upon request to the National Investment Agency.
Funding required
297,670,000 USD
RegionInfrastructure
Participation in the project
National Investment Agency
Contact the agency to receive a presentation, discuss participation terms, and next steps. The selected project will be automatically indicated in your inquiry.